What is Advanced Planning and Scheduling? A Complete Guide
/
read

Advanced planning and scheduling are embedded within a work management structured process designed to ensure reliability and continuous improvement. This process typically includes six key steps:
Recognize and define the work that needs to be done. whether it arises from inspections, failures, or improvement initiatives.
Prepare all necessary details for successful task execution, including resources, materials, tools, and safety requirements.
Create detailed time-bond timeline for executing planned work orders.
In production settings, this step is crucial for accurate modeling, resource allocation, and adapting to real-time changes.
Carry out the planned and scheduled work according to established procedures and safety standards.
Finalize all documentation, feedback, and closeout actions to ensure proper recordkeeping and accountability.
Evaluate performance, identify lessons learned, and use insights to improve future planning and scheduling activities.
Together, these six steps form a structured, closed-loop approach to managing work efficiently, driving operational reliability, improving coordination between departments, and enabling continuous improvement across the organization.
What is Advanced Planning and Scheduling?
Advanced Planning and Scheduling (APS) refers to a set of digital tools and methodologies designed to optimize how work is planned, prioritized, and executed across maintenance and production environments.
In industrial maintenance, Advanced Planning and Scheduling systems bridge the gap between strategic asset management and day-to-day execution. They integrate inputs from maintenance, operations, procurement, and reliability teams to ensure that every task, whether preventive, corrective, or predictive, is planned and scheduled in alignment with resource availability, criticality, and production goals.

The Fundamentals of Advanced Planning
Planning is the process of preparing in advance for each specific job so it can be executed with minimal disruption. It determines what must be done and how it will be done.
What Planning Covers
Planning involves multiple essential steps to ensure work is performed safely, efficiently, and in compliance with standards. It’s about preparing every aspect of the job before execution.
Key elements include:
- Defining the Job Scope: Clarifies what work will be done and sets clear boundaries for the task.
- Task Breakdown: Outlines each step required to complete the job safely and efficiently.
- Resource Identification: Determines which trades or skills are needed, how many people are required, and identifies human resources necessary for effective workforce planning.
- Materials Preparation: Includes purchasing or acquiring parts, reserving equipment (e.g., cranes or scaffolding),special tools, and coordinating specialized teams if needed.
- Safety Considerations: Covers personal protective equipment (PPE), lockout/tagout procedures, and any special permits required for the work.
- Environmental Factors: Ensures proper handling of waste or residues and compliance with environmental regulations.
By systematically addressing these elements, planning sets the stage for smoother execution, reduces risks, and ensures compliance with all regulatory and safety requirements.

Role of a Maintenance Planner
The maintenance planner plays a central role in organizing and coordinating all aspects of planned work. Their responsibilities include developing detailed work packages that outline every step required for successful execution, ensuring that all parts and materials are available beforehand, and documenting precise procedures for technicians to follow.
In addition, effective planning relies on clearly defined roles and responsibilities among all stakeholders. Each participant, from planners and supervisors to technicians and storeroom personnel, must be responsible for their part in the process to maintain a smooth workflow and deliver consistent results.
Effective maintenance planning is essential for enabling organizations to optimize resources, improve operational efficiency, and adapt to changing conditions.
Skills Required for an Effective Maintenance Planner
To perform effectively, a maintenance planner needs a combination of technical knowledge and interpersonal abilities. Success in this role relies on balancing expertise with the capacity to work well with others.
- Technical Knowledge: Understanding equipment, processes, and maintenance methods is essential.
- Teamwork: Ability to coordinate with cross-functional teams, vendors, and operations staff. Clear communication ensures tasks are understood and executed properly.
- CMMS Proficiency: Efficient management of work orders, schedules, and asset data using Computerized Maintenance Management Systems.
- Collaboration & Motivation: The ability to discuss issues, collaborate effectively, and motivate others often determines the overall success of maintenance planning.
A planner who combines technical expertise with strong interpersonal skills can streamline maintenance operations, reduce errors, and foster a more cooperative work environment.
Planning Deliverables
The planning process produces several tangible deliverables that guide and support maintenance execution:
- Job Plans: These provide detailed, step-by-step instructions for the task, including estimated labor hours, safety measures, and procedural guidance to ensure consistency and quality. Incorporating detailed sequencing in job plans ensures each step is clearly defined, optimizing execution efficiency and minimizing downtime.
- Bill of Materials (BOMs): A pre-identified list of all parts and materials needed associated to an equipment, helping reduce delays and unplanned downtime.
- Work Order Packages: Comprehensive documentation that consolidates all relevant information—job plans, permits, drawings, and BOMs—into a single reference for execution teams.
- Parts Kitting: The process of grouping and organizing all required parts and tools in advance, so technicians can access everything they need prior to the start of the job.
- Weekly Schedule: A coordinated plan that aligns upcoming work with available resources, ensuring that jobs are prioritized and executed efficiently within the scheduled timeframe with consideration to equipment availability.
The Fundamentals of Scheduling

In most organizations, the roles of planner and scheduler are often combined, even though they can be distinct. While some companies maintain separate positions, planners focusing on preparing work and schedulers on timing and sequencing, many merge these responsibilities into a single planner/scheduler role to:
- Streamline coordination between planning and execution.
- Make better use of available resources.
- Ensure seamless communication across teams.
A robust scheduling system is essential in this context, as it helps manage resources, prioritize tasks, and adapt to changing operational demands, especially as business complexity increases.
Definition and Scope
While planning focuses on what work must be done and how, scheduling determines when it will be done and who will perform it.
Scheduling is the process of arranging planned jobs into a specific sequence designed to optimize the use of available resources: personnel, equipment, and time. The main output of this process is a weekly schedule, which serves as a detailed plan for executing manufacturing activities efficiently.
What Scheduling Covers
Scheduling is a key step in turning maintenance plans into action. It ensures that resources are used efficiently and that work flows smoothly. A scheduler plays a crucial role in managing multiple tasks and dependencies, such as preventive maintenance, to ensure an efficient workflow. The main components of scheduling include:
- Resource Assignment: Allocating technicians, tools, and equipment to the appropriate tasks.
- Job Sequencing: Establishing the most logical and efficient order in which tasks should be executed.
- Asset Availability Optimization: Coordinating maintenance so that critical equipment is serviced without unnecessarily impacting production or operations.
Role of a Scheduler
The scheduler plays a critical role in turning maintenance plans into reality. Their main responsibility is to ensure that all planned work is properly prioritized, coordinated, and executed at the right time.
Key duties include:
- Balancing Labor: Allocate work across teams to avoid overload or idle time.
- Coordination with Production: Align maintenance windows with operational schedules to minimize disruptions.
- Backlog Management: Keep deferred work visible and under control, ensuring nothing is overlooked.
- Scheduling Meetings: Facilitate weekly meetings with maintenance, operations, and reliability teams to review upcoming work, resolve conflicts, and finalize the weekly plan.

Skills Required for a Scheduler
An effective scheduler combines technical expertise with strong interpersonal abilities. Success in this role depends on analyzing data accurately while coordinating smoothly across teams.
- Analytical & Technical Skills: Interpret maintenance data, resource availability, and production constraints to make informed scheduling decisions.
- Communication Skills: Clearly coordinate with multiple departments and keep stakeholders informed.
- CMMS Proficiency: Generate schedules, update work orders, and track progress efficiently using Computerized Maintenance Management Systems.
- Interpersonal Abilities: Teamwork, and abilities to discuss, listen, and negotiate effectively.
- Solution-Oriented Mindset: Being outgoing and proactive fosters collaboration and keeps scheduling meetings productive.
Scheduling Deliverables
Scheduling produces schedule that help organizations manage maintenance work effectively across different time horizons. These deliverables are structured around different planning time periods, such as days, weeks, or months, to ensure optimal resource allocation and workload balance, and to facilitate proactive planning.
– Provide a detailed, hour-by-hour allocation of specific jobs.
– Guide supervisors and technicians through the day’s priorities.
– Minimize downtime between tasks.
– Offer a balanced view of upcoming work.
– Distribute tasks evenly across available crews and trades.
– Ensure alignment with labor capacity.
– Outline high-level plans for outages, shutdowns, and preventive maintenance campaigns.
– Developed months in advance to secure materials and coordinate contractors.
– Align major interventions with operational strategy.
Together, these deliverables enable organizations to execute maintenance work efficiently, reduce reactive activities, and maintain a steady rhythm of productivity across all planning time periods.
Best Practices in Planning
Standard Job Plans
Standard job plans are essential for ensuring consistency, repeatability, and quality across maintenance operations. By using predefined templates, organizations can eliminate variations in how similar tasks are performed, improving both safety and reliability.
A standard job plan is essentially a recurring maintenance activity recorded in the CMMS, requiring minimal effort to convert into a new work order. This approach streamlines the planning process, reduces planning time, and ensures that every technician works from the same detailed and approved procedure.
Each standard job plan should include the following elements:
- Estimated duration per trade: Accurate labor estimates help optimize scheduling and balance workloads.
- Detailed description of the work performed: Step-by-step guidance ensures clarity and uniform execution.
- Parts list and required tools: Identifying materials and equipment in advance prevents delays and unnecessary trips to the storeroom.
- Safety considerations and required work permits: Ensuring all safety precautions and authorizations are in place before execution.
- Drawings, specifications, and references: Providing the necessary technical documentation to guide work quality and compliance.
By maintaining and refining these plans over time, organizations create a robust knowledge base that drives efficiency and reduces the likelihood of errors or rework.
Use of Historical Data

Using historical data is one of the most effective ways to improve maintenance planning over time. By analyzing work order feedback and reviewing past performance, planners can make more accurate labor and time estimates, better anticipate material needs, and identify opportunities to eliminate waste.
However, collecting meaningful data requires strong collaboration with technicians and tradespeople. Without open communication and teamwork, valuable information about task duration, difficulties encountered, or improvement suggestions can easily be lost or never shared.
Encouraging this feedback loop between planners and maintenance teams transforms experience into actionable insights, helping to refine job plans and continuously improve reliability performance.
Kitting and Staging of Materials
Kitting is a method used to ensure that all necessary parts and materials for a job are available and organized before work execution begins.
Each kit groups together the components required for a specific work order, typically stored in labeled containers that reference the corresponding work order number.
These kits are kept in a secure location, ready to be issued when the job is scheduled. A designated individual, often a storeroom coordinator or planner, is responsible for preparing and monitoring the kitting area to maintain organization and accountability.
The primary goal of kitting is to eliminate delays during maintenance execution by ensuring technicians have all necessary materials ready before work begins. Beyond efficiency, kitting brings several additional benefits:
- Reduced Delays: Ensures technicians have everything they need at hand, minimizing time wasted searching for parts or tools.
- Organized Storage: Allows parts for planned work orders to be stored together until the job is ready, reducing the risk of lost or misplaced components.
- Improved Flexibility: Enables teams to perform planned jobs efficiently during unscheduled production shutdowns—making the most of unexpected opportunities while equipment is offline.
Cross-Functional Collaboration
Effective planning relies on collaboration among multiple departments, including Operations, Maintenance, Procurement, and Engineering. When these functions operate in silos, inefficiencies and misaligned priorities can hinder performance.
By fostering communication and breaking down silos, organizations can better coordinate maintenance schedules with production demands, ensure timely material procurement, and incorporate engineering insights into job planning. Cross-functional collaboration ensures that all teams are aligned on goals, resource needs, and timing, ultimately improving overall equipment reliability and plant productivity.
Digital Tools and CMMS Integration
Modern maintenance planning has evolved significantly with the rise of digital tools and integration with Computerized Maintenance Management Systems (CMMS) or Asset Performance Management (APM) platforms. These systems bridge together all job plans, work orders, and historical data. In addition, scheduling software plays a crucial role in supporting digital integration by optimizing maintenance planning, enabling capacity management, scenario testing, and seamless integration with other manufacturing systems.
Key benefits of digital integration include:
- Centralized Information: Planners can store, update, and refine standard job plans over time within a single platform.
- Field Mobility: Mobile devices and tablets enable technicians to collect data directly in the field: recording feedback, updating work status, and attaching photos or notes to work orders.
- Improved Accuracy and Transparency: Real-time updates reduce errors and ensure everyone has access to the latest information.
- Continuous Improvement: Readily available data supports performance analysis and ongoing optimization of maintenance strategies.
Best Practices in Scheduling

Effective maintenance scheduling is more than simply assigning tasks to dates; it requires a structured approach that balances resources, priorities, and operational constraints. In manufacturing operations, integrating production scheduling is essential for achieving balanced and efficient maintenance execution, as it helps coordinate detailed plans for resource allocation and process optimization.
The following subsections highlight key elements of a robust scheduling process, from planning horizons to backlog management, providing practical guidance to optimize maintenance execution.
Scheduling Horizon and Resource Capacity
Effective scheduling requires careful attention to the scheduling horizon, which spans from long-term planning to weekly and daily schedules. For strategic, high-level planning, infinite capacity mode can be used to schedule without immediate resource constraints, enabling scenario analysis and easier decision making. Maintaining a consistent lookahead ensures that work is sequenced efficiently, resources are optimally allocated, and equipment downtime is minimized.
When developing schedules, the scheduler must carefully consider equipment availability, labor resources, and spare parts availability. Balancing these constraints requires skill and foresight, as adjustments in one area can have cascading effects on others.
Frozen Weekly Schedule
A key principle of effective scheduling is the use of a frozen weekly schedule. Once the schedule is finalized, it should remain stable to protect efficiency and prevent disruptions caused by last-minute changes. Adhering to this discipline ensures that planned work can proceed without interruption and resources are used as intended.
A golden rule for frozen schedules is to avoid placing work orders on the schedule until all materials, parts, and approvals are confirmed.
This prevents delays during execution and reinforces confidence among both maintenance and operations teams that the planned work will be completed efficiently as expected.
Managing Backlog
Prioritization
Managing backlog is a critical aspect of scheduling. The backlog includes all identified and approved work that is waiting to be performed. Schedulers must use risk-based decision-making to prioritize overdue work, ensuring that tasks with the highest safety, reliability, or operational impact are addressed first.
Backlog Measurement
Measuring backlog helps organizations plan and allocate resources effectively. It allows managers to:
- Determine the required maintenance manpower to complete outstanding work.
- Anticipate additional resource needs, such as contractors, overtime, or moving resources between areas.
- Allocate maintenance resources efficiently across different areas of the plant, ensuring balance and coverage.
Effects of Backlog Size
The size of the backlog can significantly affect operational performance.
Makes it challenging to assign priority work effectively to the maintenance crew.
Schedule break in tend to increase, leading to idle time and inefficiency.
Becomes difficult to control and prioritize work.
Erodes production’s confidence that maintenance will complete tasks as planned.
Increases the risk that minor issues may escalate into major failures.
Encourages the creation of “emotional emergencies,” where unplanned disruptions dominate priorities.
Common Pitfalls and How to Avoid Them
Effective planning and scheduling require not only technical knowledge and organizational skill but also vigilance against common pitfalls that can undermine performance. Unlike traditional methods which often lack flexibility and real-time data integration, modern approaches address these limitations with dynamic, technology-driven solutions.
Overloading or Underloading Schedules
One of the most frequent mistakes in scheduling is either overloading or underloading work schedules. Overloading sets unrealistic expectations for crews, leading to rushed work, decreased quality, and increased stress.
Conversely, underloading may appear to create breathing room, but it can result in underutilized resources and inefficiency. Maintaining a balanced workload is essential, ensuring that teams have enough tasks to remain productive without being stretched beyond capacity.
Poor Planning Quality
Incomplete or insufficiently detailed job plans are another major pitfall. When critical steps, parts, or safety considerations are missing from a plan, technicians are forced to improvise or revisit tasks, creating unnecessary rework. High-quality planning requires thorough documentation, accurate material lists, and clear, step-by-step instructions to minimize mistakes and streamline execution.
Lack of Cross-Department Buy-in
Schedules will only be effective if all relevant departments are engaged in the process. When operations, maintenance, and equipment owners are not involved, planned work can be ignored or delayed, leading to conflicts and inefficiencies. Engaging key stakeholders early ensures alignment, resource availability, and mutual accountability, creating schedules that are respected and adhered to.
Reactive Culture
A reactive maintenance culture, dominated by unexpected breakdowns, can quickly derail carefully planned work. Organizations that respond primarily to emergencies may find it difficult to execute planned corrective work, preventive maintenance or improvement projects.
Over-Reliance on Tools Without Process Discipline
Finally, relying solely on software or digital tools without established processes and disciplined execution is a common mistake. While CMMS, APM platforms, and other digital solutions are powerful, it is important to recognize that traditional tools often lack the adaptability needed in dynamic manufacturing environments. These traditional tools are insufficient for modern needs, and even advanced digital solutions cannot compensate for poor planning, inadequate communication, or weak coordination.
Tools must be used in conjunction with sound processes, well-trained personnel, and clear standards to deliver their full value.
Advanced Strategies
As organizations mature in their maintenance and reliability practices, advanced strategies in planning and scheduling can drive greater efficiency, reduce risk, and optimize resource use. Successful adoption of these advanced strategies often depends on careful APS implementation, which requires thorough planning, high data quality, and organizational readiness to ensure effective deployment. These strategies go beyond standard job plans and routine scheduling to align work with criticality, asset health, and major operational events.
Risk-Based Work Prioritization
One key strategy is risk-based work prioritization, which focuses maintenance efforts on the most critical assets first. By assessing the potential impact of asset failure on safety, production, and costs, organizations can allocate resources to tasks that provide the greatest value. Criticality ranking ensures that high-risk equipment receives timely attention, preventing unplanned downtime and reducing operational risk.
To further refine prioritization, organizations often use a risk prioritization matrix. This tool evaluates work based on multiple factors, such as potential impacts on production, worker safety, regulatory compliance, and environmental consequences. By combining these factors into a structured matrix, planners and schedulers can make objective, data-driven decisions about which tasks require immediate attention and which can be safely deferred.
Integration with Predictive Maintenance (PdM)
Integration with predictive maintenance (PdM) programs allows scheduling to be informed by real-time asset health data. Condition-based scheduling triggers maintenance activities based on actual equipment performance, rather than fixed intervals. Machine learning algorithms can enhance predictive maintenance by analyzing large volumes of operational data to improve forecast accuracy and enable more precise scheduling decisions.
This approach ensures that work is performed only when necessary, optimizing resource allocation, reducing unnecessary maintenance, and improving overall reliability. By aligning planned work with predictive insights, organizations can proactively address emerging issues before they escalate into failures.
Shutdown and Turnaround Planning
Large-scale maintenance events, such as plant shutdowns or turnarounds, require dedicated planning and scheduling processes. These events often involve multiple teams, contractors, and complex coordination to complete high-impact work within a constrained timeframe.
Advanced scheduling strategies ensure that resources, materials, and activities are sequenced optimally, minimizing downtime while maximizing productivity. Proper planning for these major events also reduces safety risks, ensures compliance with permits and regulations, and allows for thorough post-event analysis to capture lessons learned for future operations.
By incorporating risk-based prioritization, predictive maintenance integration, and structured shutdown planning, organizations can achieve a more proactive, efficient, and resilient maintenance program that aligns with both operational goals and business objectives.
Measuring and Improving Planning & Scheduling Performance
To ensure that planning and scheduling processes are effective, organizations must track key performance metrics and implement continuous improvement cycles. Monitoring inventory levels is also crucial, as up-to-date inventory data supports accurate performance tracking and effective scheduling. Measuring performance not only highlights areas of strength but also identifies opportunities for refinement and increased efficiency.
Key Metrics in Planning & Scheduling
Planning Accuracy
Planning accuracy compares the estimated labor, time, and resources outlined in job plans with actual results. High planning accuracy indicates that estimates are realistic and work is well-prepared, while low accuracy signals the need to improve planning methods or incorporate lessons from past tasks.
Schedule Compliance

Schedule compliance measures the proportion of planned work that is completed as scheduled. This metric provides insight into how effectively resources are allocated, whether scheduling conflicts are being managed, and whether unplanned disruptions are impacting operations. High compliance reflects a well-coordinated maintenance program, while low compliance highlights potential issues with resource availability, planning quality, or operational cooperation.
Backlog Health
Backlog health evaluates the volume of pending work, typically expressed in weeks of backlog. Monitoring backlog levels allows organizations to determine whether they have sufficient manpower, anticipate the need for additional resources, and maintain balance across plant areas. Healthy backlog levels support proactive maintenance, while excessive or insufficient backlogs can compromise reliability and workflow efficiency.
PM Compliance
Preventive maintenance (PM) compliance tracks the completion of scheduled PM tasks. High PM compliance ensures that preventive activities are executed on time, reducing the likelihood of unexpected failures and extending asset life.
Scheduling Efficiency (Volume of Scheduled Work)
Comparing the level of scheduling with the available labor hours helps measure how effectively work is distributed among crews. This metric ensures that workloads are balanced and resources are neither overburdened nor underutilized, promoting both productivity and employee engagement.
Continuous Improvement Cycles
Continuous improvement relies on feedback loops that capture lessons learned from completed work. Post-job reviews allow teams to evaluate what went well, identify challenges, and refine job plans and processes. By incorporating this feedback into future planning and scheduling activities, organizations can improve accuracy, reduce waste, enhance safety, and drive consistent operational excellence.
Together, measuring performance through key metrics and applying continuous improvement cycles ensures that planning and scheduling evolve as dynamic processes, adapting to operational realities while consistently enhancing reliability, efficiency, and overall maintenance effectiveness.
Conclusion
Effective planning and scheduling form the backbone of a successful maintenance and reliability program. APS solutions offer a comprehensive approach to optimizing planning and scheduling by integrating data collection, visualization, and constraint management. From defining the scope of work and developing detailed job plans to creating efficient schedules and integrating advanced strategies like risk-based prioritization and predictive maintenance, each step contributes to improved efficiency, reduced downtime, and optimized resource utilization.
Measuring performance through key metrics such as planning accuracy, schedule compliance, backlog health, and PM completion provides actionable insights, while continuous improvement cycles ensure that lessons learned are incorporated into future planning and scheduling efforts. Advanced strategies, including condition-based scheduling and structured shutdown planning, allow organizations to align work with both operational priorities and business objectives, further enhancing reliability and performance. Advanced planning and scheduling can be integrated with enterprise resource planning systems for a unified digital approach or used as a standalone system to independently optimize production and resource planning.
As Michel Coté, one of the collaborators involved in building this article, wisely observed:
Typically, the greatest challenge and resistance we face when deploying planning and scheduling is the culture. Unfortunately, we can’t change a plant’s culture by the simple click of a button.
This quote serves as a reminder that while tools, processes, and strategies are critical, the human and cultural element ultimately determines the success of planning and scheduling initiatives. Achieving lasting improvements requires patience, consistent communication, and a commitment to fostering a culture that values proactive, well-coordinated maintenance practices. Seamless integration between APS solutions and other business systems is also essential for enabling real-time data exchange and supporting dynamic, effective planning and scheduling.

MIchel Cote,
Laurentide Controls
[email protected]